MARCH 2019: CONSTRUCTION UPDATE

The new “Heart of Coral Gables” has a strong pulse. Now in the  9th month of vertical construction on the North parcel, The Plaza Coral Gables team is making great progress towards its goal of a summer 2020 completion for this phase of the project.  The 14 story Class “A” office building in the North […]

DEVELOPMENT UPDATE: CONSTRUCTION OF NORTH PARCEL IS FULL STEAM AHEAD

Construction work on the North Parcel at the site of The Plaza Coral Gables continues to progress as work is being completed on the 3rd floor.  General contractor, Coastal-Tishman Construction, is building the parcel’s office and retail space as well as a residential tower. In the heart of the City Beautiful, The Plaza Coral Gables […]

THE PLAZA CORAL GABLES REVEALS FINAL DESIGN AND CONSTRUCTION PLANS

MIAMI, Fla., September 20, 2018 – The Plaza Coral Gables— the largest, mixed-use, development within the City of Coral Gables—revealed today its final design and construction plans, which include a one acre ‘open plaza’ extending to a dramatically enhanced Ponce Circle Park. In the heart of the City Beautiful, The Plaza Coral Gables brings a luxury […]

DEVELOPMENT UPDATE: JULY 2018

After years of planning and pre-construction efforts, we are officially “Going Vertical”. We received the first Master Building permit from the City of Coral Gables on July 10th.  This is a major milestone which allows all aspects of construction in the North parcel to proceed.  Foundation work and underground utility work will continue, immediately followed […]

DEVELOPMENT UPDATE

We are proud to announce that we have selected Coastal-Tishman as the general contractor for our first packages of the project “THE PLAZA CORAL GABLES”.  Coastal Tishman is one of South Florida’s premier construction management firms and a great asset to our development team. While we wait for the issuance of the first master building […]

TEMPORARY STREET CLOSURES

“THE PLAZA CORAL GABLES” Development Team is pleased to announce that the site preparation continues full speed ahead in order to be able to start the construction activities in the first quarter of 2018. As the preliminary works (demolition, backfilling and material transportation) plus the future construction activities occur on all parcels of the Project Site […]

CURB IMPROVEMENT ON MALAGA AVENUE

Permits are in place and work is scheduled to commence during the first 2 weeks of October for the improvement of the road alignment and street curb on Malaga Ave. (between Ponce de Leon and Coconut Grove Drive). The work is scheduled to last between 1 and 1 and a half weeks. These improvements are necessary […]

OCTOBER CONSTRUCTION UPDATES

We would like to share the latest news on our construction activities. NORTH PARCEL: The North Parcel between, Sevilla and Palermo Aves. has been filled with material and compacted to street level (covering the hole that was left open several years ago when the old office tower was demolished). We have started preliminary structural construction […]

NORTH PARCEL PRE-CONSTRUCTION PROGRESS

The Plaza Coral Gables continues working on the site located between Sevilla and Palermo streets, known as “North parcel”. Keeping up with this effort, we are still targeting an early 2018 groundbreaking. While the design and the entitlement process is ongoing “behind the scenes” for the overall project, today you can see our crews actively […]

PRE-CONSTRUCTION ACTIVITIES

We wish to anticipate that the start of the construction execution stage is scheduled for the first quarter of 2018.  Prior to the “official” groundbreaking, the plan is to continue and complete pre-construction activities that involve removing leftover elements from the basement located in the north parcel, remove any abandoned underground utilities, and fill the […]